ASSIGNMENT 4 COST BENEFIT ANALYSIS QUESTION A QUESTION B QUESTION C This project is feasible because profilability index > 1 , so this is good investment
Network Diagram and Critical Path 2 Critical Path = 1, 2, 3, 4, 6, 8 || 1, 2, 3, 4, 8 = A,1 , B,1 , C,2 , F,4 , E,3 , H,1 || A,1 , B,1 , C,2 , F,4 , I,2